| Date | Activity |
Status | Comment |
| October 28 | PO Hult and Klas Hultqvist leaving for
Christchurch | | |
| October 30 | Christin Burgess and Thomas Burgess
leaving for Christchurch | | |
| November 1 | PO and Klas in McMurdo | | |
| November 3 | Christin and Thomas in McMurdo |
| November 4 | Team assembles at Pole |
All four members are at Pole | |
| November 5 | Pick-up boxes will arrive |
All equipment arrived | Everything is in MAPO unpacked |
| November 6 | Two pick-up boxes (40 channels) will be replaced.
Prior to replacement, waveforms and noise (with and without the VLF running)
will be measured for the 40
channels and for 20 reference channels in the same string. After the
replacement the new pick-up boxes will be left running until Sunday to check
satbility. Meanwhile waveforms and noise will be measured for three
channels in each of the remaining strings, one in the top, one in the
middle and one in the bottom. | Done. | The noise has
increased. |
| November 7 | If the two new pick-up boxes are working, the
remaining 34 pick-up boxes will be changed too. |
Partly done. | The two pick-up boxes give higher noise than
before, due to the 1458 (2003) power supply. This has been
investigated. The noise can be strongly reduced by moving the quad
cables away from the power supply and changing the bandwidth of the
SWAMP card. Two new pick-up boxes have been put in string 1 (B4
01/04) and string 12 (B13 05/06). The VLF signal is blocked and the
noise levels are the same as before the replacement. |
| November 8 | Check the noise levels in B4 01/04 and B13
05/06 again, and if it looks good continue to change pick-up
boxes. | Done. | Noise levels stable and unchanged, all
pick-up boxes have been replaced. |
| November 9 | Change all pick-up boxes, change bandwidths
| Done. | |
| November 10 | Wait for monitoring file 313_8094 to check
detector status after change, fix problems if there are any
| Run 313_8094 got stuck, checked run 314_8095 instead. |
|
| November 11 | Wait for monitoring file 314_8095 to check
detector status after bandwidth change, fix problems if there are any
| Run 8095 checked, some problems fixed. | OM 94 still
dead. |
| November 12 | Fix OM 94 and pack old equipment for
shipping back to Stockholm. Evaluate new run.
| OMs 94 and 404 fixed. | |
| November 13-? | Consider changing HV settings and DMADD
thresholds
| | |
| November 18 | Per Olof and Klas leave South Pole
| | |
| November 22 | Christin and Thomas leave South Pole
| | |