Planning

DateActivity StatusComment
October 28PO Hult and Klas Hultqvist leaving for Christchurch
October 30Christin Burgess and Thomas Burgess leaving for Christchurch
November 1PO and Klas in McMurdo
November 3Christin and Thomas in McMurdo
November 4Team assembles at Pole All four members are at Pole
November 5Pick-up boxes will arrive All equipment arrivedEverything is in MAPO unpacked
November 6Two pick-up boxes (40 channels) will be replaced. Prior to replacement, waveforms and noise (with and without the VLF running) will be measured for the 40 channels and for 20 reference channels in the same string. After the replacement the new pick-up boxes will be left running until Sunday to check satbility. Meanwhile waveforms and noise will be measured for three channels in each of the remaining strings, one in the top, one in the middle and one in the bottom.Done.The noise has increased.
November 7If the two new pick-up boxes are working, the remaining 34 pick-up boxes will be changed too. Partly done.The two pick-up boxes give higher noise than before, due to the 1458 (2003) power supply. This has been investigated. The noise can be strongly reduced by moving the quad cables away from the power supply and changing the bandwidth of the SWAMP card. Two new pick-up boxes have been put in string 1 (B4 01/04) and string 12 (B13 05/06). The VLF signal is blocked and the noise levels are the same as before the replacement.
November 8Check the noise levels in B4 01/04 and B13 05/06 again, and if it looks good continue to change pick-up boxes.Done.Noise levels stable and unchanged, all pick-up boxes have been replaced.
November 9Change all pick-up boxes, change bandwidths Done.
November 10Wait for monitoring file 313_8094 to check detector status after change, fix problems if there are any Run 313_8094 got stuck, checked run 314_8095 instead.
November 11Wait for monitoring file 314_8095 to check detector status after bandwidth change, fix problems if there are any Run 8095 checked, some problems fixed.OM 94 still dead.
November 12Fix OM 94 and pack old equipment for shipping back to Stockholm. Evaluate new run. OMs 94 and 404 fixed.
November 13-?Consider changing HV settings and DMADD thresholds
November 18Per Olof and Klas leave South Pole
November 22Christin and Thomas leave South Pole

Back

Last updated: November 18, 2004